January 10th, 2006
All,
At the recent committee meeting some members were asking how they could
get more involved with the new-field project.
A quick update on the
pavilion:
The three portacabins have been knocked through into one building. The
roof over it is almost complete. The balcony has its frame up and awaits
the planking to go down.
The remaining work is basically skilled or semi-skilled: electrics,
plumbing including showers and boiler, kitchen fitting, sewer work, a
little ground work, decoration. All this has been 'subbed out' to
skilled volunteers who are not charging for their services.
Tthe work on
the pavilion is, therefore, largely allocated.
There are, however, several jobs which need doing for the field to be
ready for cricket next year. These include:
Completing the car park (this will be a spring job under the direction
of 'Phil Brown the builder').
If anyone wants to take on any particular job please contact either
myself or Pete Jones.
If you wish to see the progress that has been
made, or if you have a couple of hours to spare, again contact Pete or
myself. Pete is down there most days and would appreciate a little help
- even if it is something simple like clearing the rubbish from the
pavilion.
Cheers,
Phil